# 2026-02 Sherwood P1871 Installation Notice Conflicts with Completion Form
Flock gave ARDOT a February 2, 2026 “start work notice” under P1871 “to install 2 ALPR devices,” forecast for February 13 (`FW__Pre-Con_Email.pdf`, p. 1). The same permit packet contains a City completion form dated June 11, 2025 ([[Sherwood Highway 107 Permit P1871]], `SP-06-2025-0017...Approval_Signed_Updated.pdf`, p. 6).
## Significance
The sequence is unresolved. It could reflect replacement/reinstallation, a subset of sites, a stale notice, or an inaccurate completion form. The corpus does not select among those explanations; [[T009 - Sherwood ALPR Completion and Installation Chronology]] remains open.